SITE VISIT:
We
strongly encourage subcontractors to visit the construction site prior to
submitting a proposal. A site visit can
be set-up with the Project Manager or Estimator.
GENERAL NOTES:
In regards to the above referenced project, Penzel is preparing a
proposal as General Contractor and is currently requesting subcontractor and
material supplier proposals.
The Project Engineer is Koehler Engineering & Land Surveying, 194 Coker Lane,
Cape Girardeau, Missouri, 63701. Phone: (573) 335-3026.
Plans may be viewed at Penzel's Office or on this Web Site, or purchased from
the Engineer's Office for a non-refundable fee of $100.00 per set.
We request your quotation on or before 5:00 p.m., Tuesday,
September 4,
2012.
We recommend that you frequently check our website for project updates.
If you have any questions, do not hesitate to contact us.
Prevailing wages for the State of Missouri or the Federal Wage Rate
(whichever is higher) must be paid for this job.
Faxed bid forms will be accepted until Bid Time.
Subcontractors are responsible for confirmation of receipt of the bid
form via a follow up phone call to the Penzel point of contact.
Penzel Construction Company, Inc., the Owner, and all other parties
as required by the contract are added as primary additional insured under
Subcontractors Comprehensive General Liability policy.
For additional information see “project insurance requirements” on this
web site.
Subcontractors are required to adhere to all Penzel, and OSHA
Safety Policies. The Penzel Standard
Form Contract will be utilized without modification for all subcontractors.
A copy of the Penzel Safety Policy or Standard Form Contract is available
upon request. The OSHA Safety and
Health Requirements Manual is available on the OSHA web site at www.osha.gov.
Subcontractors are urged to review the plans, specifications, and
all associated addendums that were used for design of this project.
Subcontractors are responsible for cleanup of material and waste
associated with their scope of work.
Clean-up will be coordinated with the on-site superintendent and will be
performed on a daily basis. If the
subcontractor is deemed unresponsive to this requirement, Penzel will perform
the activity at the expense of the subcontractor.
This project is tax exempt.
Missouri sales and/or use taxes are NOT applicable to permanent materials
on this project.