SITE VISIT:
We
strongly encourage subcontractors to visit the construction site prior to
submitting a proposal. A site visit can
be set-up with the Project Manager or Estimator.
GENERAL NOTES:
In regards to the above referenced project,
Penzel is preparing a proposal as General Contractor
and requests subcontractor
and
material supplier quotes.
There is a 365 Calendar
Day construction schedule with Liquidated Damages of $1,050.00 per calendar
day
for not completing on time.
This project
consists of Civil/Site
work
and
a two (2)
story
building
over a full basement, with the basement level approx. 9, 875 sf, Main level
approx. 14.879 sf,
and
upper level approx. 9,875 sf. Building includes offices, Sallyport, holding
cells, dispatch center, etc. Building exterior to be masonry veneer over CMU
bearing walls, steel columns and beams. Membrane roof system over steel
joists. Interior is primarily CMU and metal stud walls. The
work includes, but is not limited to, Civil, Architectural, Structural,
Mechanical, Plumbing,
Fire
Protection,
and
Electrical components
and
systems. There
are
Three (3) Alternates.
The project Architect is Dille and Traxel, LLC.,
1323 Maud Street,
Poplar Bluff, Missouri 63901. Phone: 573-778-0033. Bidding Documents are
available from the Architect, at Penzel’s office - 325 West Jackson Blvd.,
Jackson,
Missouri 63755, or on this web site. In addition, drawings and specification
sections may be obtained through Penzel’s office. Bid documents may also be
viewed at the Architect’s office, AGC of Missouri in Jefferson City , Missouri,
and McGraw-Hill Construction Dodge in Springfield Missouri.
Material substitutions from the specifications
must be approved by the Architect prior to bidding.
The project is being funded in whole,
or in part, by the American Recovery
and Reinvestment Act
and
has certain requirements for iron, steel and manufactured goods that must be
strictly adhered to in accordance with the ‘Buy American’ provisions. All
participants must comply with Federal regulations including Wages as Determined
by the Secretary of Labor in accordance with the provisions of the Davis-Bacon
Act, and current prevailing wage rates, as set by the Missouri Department of
Labor under Wage Order No. 17 for Scott County. The higher of the two rates
MUST BE PAID. Please examine the Specification Pages - General Conditions for
compliance issues regarding Federal Government policies.
We request your
quotation on or before
5:00 p.m.,
Wednesday, March 9th, 2011.
Sales Taxes shall not be included in
bids. The Owner will issue a tax exempt letter for materials incorporated in
the work.
We recommend that you frequently check our
website for project updates. If you have any questions, do not hesitate to
contact us.
Faxed bid forms will be accepted until Bid
Time. Subcontractors are responsible for confirmation of receipt of the bid
form via a follow up phone call to the Penzel point of contact.
Subcontractors are required to
include the Owner and Penzel as additionally insured.
Subcontractors are required to
adhere to all Penzel and OSHA Safety Policies. The Penzel Standard Form
Contract will be utilized without modification for all subcontractors. A copy
of the Penzel Safety Policy or Standard Form Contract is available upon
request. The OSHA Safety and Health Requirements Manual is available on the
OSHA web site at www.osha.gov.
Subcontractors are urged to review
the plans, specifications, and all associated addendums that were used for
design of this project.
Subcontractors are responsible for
clean up of material and waste associated with their scope of work. Clean-up
will be coordinated with the on-site superintendent and will be performed on a
daily basis. If the subcontractor is deemed unresponsive to this requirement,
Penzel will perform the activity at the expense of the subcontractor.
This project is tax exempt. Missouri
sales and/or use taxes are NOT applicable to permanent materials on this
project.